DCMA schedule review: what the 14 criteria reveal about a construction schedule

A schedule can look convincing on paper and still fail to forecast anything. The DCMA 14-Point Assessment checks whether the logic of a schedule holds before anyone argues about dates. This article explains the 14 criteria, their thresholds and what they mean in infrastructure construction.

By Sergius Winter · 24 November 2026 · 9 min read

What it is about

The DCMA 14-Point Assessment originates from the Defense Contract Management Agency, the contract audit agency of the US Department of Defense. It was developed to review contractor schedules against a uniform standard of technical quality. Today it is the most widely used benchmark for whether a network schedule is computationally sound.

The review says nothing about whether the construction sequence is right. It checks the mechanics: are all activities linked, are there artificial constraints, do float and durations make sense, is the schedule updated. Only when the mechanics work is a content review worthwhile, because only then does the software calculate the consequences of a delay correctly.

In German infrastructure construction the method is still rare. The VOB/B requires a construction schedule but sets no quality requirements. That is the gap the review fills: it gives the owner objective, traceable criteria to accept a submitted schedule or return it for revision.

The review basis

Before the criteria are checked, the set of activities that count is defined. Only open activities with a duration are reviewed. Milestones, summary activities, completed activities and activities that only represent a possession or a calendar are excluded. This step matters because a schedule with many summary activities would otherwise look better than it is.

The 14 criteria

Thresholds follow the DCMA scheme. Working-day figures (WD) refer to 44 WD, roughly two months.

No.CriterionThresholdWhat it means
1Activities without predecessors≤ 5 %An activity without a predecessor starts at project start by calculation. If anything before it moves, the schedule does not notice.
2Activities without successors≤ 5 %An activity without a successor has no effect on project completion. Its delay stays invisible.
3Negative total float0 %Negative float means the schedule does not meet its own dates. Every such activity is an unresolved conflict.
4High total float≤ 5 % over 44 WDVery large float points to missing links or to activities that are not part of the sequence.
5Hard constraints≤ 5 %Constraints such as “must start on” override the logic. The schedule then shows dates that cannot be reached by calculation.
6Missing resources≤ 5 %Only relevant if the schedule carries resources. In infrastructure this criterion often does not apply because resources are not modelled in the construction schedule.
7Long activity durations≤ 5 % over 44 WDLong activities hide progress. A six-month activity reports “on plan” for three months without anyone being able to check.
8Invalid dates0 %Actual dates in the future or forecast dates in the past. Shows the schedule was not updated properly.
9Logic errors0 %Circular dependencies or links to summary activities. The software calculates them wrongly or not at all.
10Leads0 %Negative lags (“successor starts 10 days before the predecessor ends”) are hard to trace and are often used as a float trick.
11Lags≤ 5 % over 44 WDLong positive lags replace activities missing from the schedule, such as approvals or lead times. They should be modelled as activities.
12Missed activities≤ 5 %Activities whose planned finish has passed without completion. The measure of how far schedule and site have drifted apart.
13Fixed-duration activity type≤ 5 %Concerns resource-loaded schedules. Fixed-work activities change their duration unnoticed when resources change.
14Update frequency≤ 30 daysA schedule not updated for more than a month is useless for control, however good its logic.

What the criteria mean in infrastructure construction

Not every criterion carries the same weight in every project phase. Before construction starts, when the contract schedule is reviewed, open ends and constraints weigh heavily: they decide whether the schedule can serve as a baseline at all. During execution, missed activities move to the front because they measure the actual slippage. Shortly before completion, negative float and update frequency count most, because every week of delay now hits acceptance directly.

From our practice, three findings are particularly common. First, hard constraints: many schedules pin milestones to the contract dates instead of building the logic so that the dates follow from it. The schedule then looks green until the first activity actually slips. Second, long durations on civil structures: an activity “build superstructure” with 180 days cannot be controlled. Third, missing predecessors on design and approval steps that sit in the schedule as isolated blocks even though construction depends on them.

Possessions on rail projects are a special case. They are often modelled as fixed-duration, constrained activities, which loads two criteria at once. The better approach is a milestone or calendar exception with the dependent works linked to it. The schedule then recognises a missed possession and shows the consequences for the next one.

Weighting and rating

The original DCMA scheme rates each criterion only as pass or fail. For practice that is too coarse, because a single activity without a successor means something different in a 2,000-activity schedule than in one with 80.

We therefore work with weighted criteria that add up to 100 points. The weights depend on the project phase: for the contract schedule, open links and constraints count most; during execution, missed activities and leads; in the final phase, negative float. Criteria the schedule does not model, such as resources, are dropped and the score is normalised to the criteria reviewed.

ScoreRatingMeaning for the owner
80 to 100ApprovableThe schedule works as a control instrument. Individual findings are noted.
65 to 79Conditionally approvableThe schedule is accepted; findings are to be resolved by the next update.
50 to 64Revision requiredThe schedule is returned for revision. Dates from it are not reliable.
below 50RejectedThe schedule does not serve its purpose. Rebuilding is more economical than correcting.

An example

A fictitious schedule for a bridge with 240 activities, reviewed in the execution profile: 12 activities without successors (5 %), 9 hard constraints (4 %), 31 activities longer than 44 working days (13 %), 18 missed activities (8 %), last update 19 days ago. All other criteria met. Result: 71 of 100 points, conditionally approvable.

The rating is not the end of the review but its start. The 31 long activities must be split, otherwise progress stays invisible until completion. The 18 missed activities show where the site is behind the schedule and are the entry point for the discussion with the contractor. That is the professional level no software replaces.

Limits of the method

  • The review rates logic, not content. A schedule with 95 points can still have unrealistic durations or missing scope.
  • The thresholds are convention, not natural constants. In a 60-activity schedule a single outlier is already 1.7 percent.
  • The scheme comes from US defence procurement. For German construction contracts under VOB/B there is no normative basis; the review is a professional agreement between the parties.
  • There is no DCMA certification. Anyone reviewing “DCMA-certified” is using the term wrongly.

How we review

PM CTRL reviews schedules on three levels. The first is technical integrity against the 14 criteria, automated with our software CTRL SCAN, which evaluates MS Project XML and Primavera XER locally in the browser without the schedule leaving the computer. The second is operational feasibility: missing scope, possessions, interfaces, durations. The third is forecast value: can the schedule justify decisions.

The output is a review report with findings per criterion, affected activities and recommendations. It describes what the schedule contains and what has changed. It makes no statements on causes or responsibility; that remains a matter for contractual review.

Frequently asked questions on this topic

Which schedules can be reviewed?

Any network schedule with logic links, i.e. schedules from MS Project, Primavera P6 or comparable software. Bar charts without logic, for example in Excel, cannot be reviewed; the mechanics being checked are missing.

How long does a review take?

The technical review against the 14 criteria takes minutes with software. The professional assessment of the findings and the discussion with the contractor are the real effort, one to three days depending on the schedule.

Can the owner reject a schedule because of a poor DCMA rating?

That depends on the contract. The VOB/B sets no quality criteria. It is advisable to define the requirements for the schedule in the particular conditions of contract; the review is then contractually secured.

Terminplanprüfung · DCMA 14-Point Assessment · Termincontrolling · MS Project · Primavera P6

Want your schedule reviewed?

Briefly describe the project, its phase and what you need. We will get back to you on your enquiry.